Key facts

  • •It acts on the demand charge, not the energy rate.
  • •Height of the peak above the ceiling sets the power rating (kW).
  • •Duration of the peak sets the energy required (kWh).
  • •Frequency of peaks decides whether there is time to recharge, and how many cycles a year accumulate.
  • •It needs interval load data: fifteen-minute readings for at least twelve months.

How it works

The control system watches incoming load and tells the battery to discharge as demand nears the ceiling. Between events the battery recharges during low-demand periods or from on-site solar.

The ceiling is the key decision. Too low, and the battery runs out mid-peak and the spike gets through, wasting the month’s effort. Too high, and savings are left on the table. It should come from the load data and hold on the worst day in the dataset, not a typical one.

Worked example

These figures are illustrative. A site peaks at 720 kW and sets a ceiling of 600 kW, so the battery must supply 120 kW. The longest peak above the ceiling lasts 45 minutes, which needs 120 × 0.75 = 90 kWh delivered.

If only 80 per cent of nameplate capacity is usable, that is 90 ÷ 0.8 = 112.5 kWh nameplate, before margin for losses and fade. Power, not energy, is the demanding figure: 120 kW from 112.5 kWh is about 1.07C.

At an illustrative ₹400 per kW per month, 120 kW less billed demand is worth ₹48,000 a month, or ₹5,76,000 a year, if the billing rules let the full reduction through and the battery covers every peak.

Why it matters to a buyer in India

Peak shaving is usually the most dependable part of a commercial battery case, because the saving comes from the demand charge and is less sensitive to round-trip losses than shifting energy between tariff periods. The same battery can also do time-of-day shifting, solar storage and backup, provided the controls know which duty comes first.

Those duties compete. Energy held for backup, or spent earlier in a ToD window, is not available when a spike arrives, and a single miss can set the month’s demand charge.

Common mistakes

Check these in any proposal:

  • •Sizing from monthly bills rather than interval data.
  • •Ignoring capacity fade, so a battery that covers every peak on day one stops doing so later.
  • •Not confirming whether, and how quickly, your DISCOM will let you reduce contracted demand.
  • •Leaving unstated who carries the risk if the system misses a peak and you are billed anyway.

Frequently asked questions

What is the difference between peak shaving and energy arbitrage?+

Peak shaving lowers the highest load the meter records, which reduces the demand charge. Energy arbitrage moves units from an expensive period to a cheap one, which reduces the energy charge. One battery can do both, but a sensible control strategy holds a reserve for shaving and arbitrages with what remains.

Can solar panels do peak shaving without a battery?+

Only by chance. Solar output lowers daytime grid draw when the sun happens to coincide with the peak, but it cannot be relied on for a peak that arrives on a cloudy day or in the evening. Demand is billed on the worst interval, so one uncovered peak is enough to set the charge.